Dataset: Transect Precipitation


   Download data: File tranprec.dat
   File description including attribute definitions: data_JornadaStudy_003_transect_precipitation_direct_reading_raingauge_weekly
   Original Investigator: Marsha Conley
   Data contact: John Anderson
   Duration: 1982 - 1986
   Dataset ID: 210003001
   Abstract:

Precipitation is recorded weekly at each of the 91 sampling stations located 30m apart along the LTER-I Control Transect from a direct- reading rain-gauge attached to the west cross-arm of the station marker.


   Additional information:

In the spring of 1982, as part of the establishment of the Jornada Long-Term Ecological Research site in southern New Mexico, a 135 ha portion of a 1500 ha, internally drained, watershed was exclosed from grazing by domestic livestock. Prior to exclosure the watershed, as well as the rest of the Jornada basin, had been moderately to heavily grazed for the past 100 years. Concurrent with grazing, the vegetation had undergone a dramatic change from desert grassland, with an almost continuous cover of C4 perennial grasses, to isolated patches of the original grassland in a mosaic with desert shrub dominated plant communities (Buffington and Herbel, 1965). The exclosure lies along a northeast facing piedmont slope at the base of a steep isolated mountain peak, and covers a variety of component landforms from the foot of the mountain to the basin floor. The northeast side of the exclosure is immediately upslope of the College Playa located near the NMSU College Ranch. Three parallel transects (2.7 km in length) run from the middle of the College Playa up into the foot of Mt. Summerford. The Control transect is to the west, the Treatment transect on the east side of the Control transect, and the Alternate Control to the east of the Treatment transect. Each transect is 30 meters wide with a 45 meter buffer zone between each transect. The Treatment transect was treated annually until 1987 with NHNO3 in a concentration equal to 10g N/m2. The station markers at 30 meter intervals along each transect.

   Methods:

Field data sheets

   Methods:

Attached to the west arm of each station marker along the control transect is a direct-reading rain gauge tru-check. The amount of precipitation occurring during the week is recorded. The gauge is emptied and bugs and dirt cleaned out with a water squirt-bottle and a stiff-wire. A few drops of mineral oil are then added to prevent evaporation of precipitation from the gauge.

   Maintenance:

weekly

   Quality Assurance

Data were analyzed (statistics files noted) but analysis program is unknown.